6.1
The proposed
project involves the decommissioning, demolition and decontamination of the
Cheoy Lee Shipyard (CLS) at Penny’s Bay to provide land for the construction of
Hong Kong Disneyland Phase 1 and its associated infrastructure. Wastes to be generated during
decommissioning and demolition are expected to comprise excavated spoil,
construction and demolition (C&D) material, asbestos-containing material
(ACM), general refuse, abandoned equipment, and chemical waste.
6.2
Under the Air
Pollution Control Ordinance (APCO), asbestos surveys were carried out in March
2001 and April 2001 for visual inspection and sampling of ACM. Such findings have been documented in
the Asbestos Investigation Report (AIR) and recommendations to remove ACM have
been detailed in the Asbestos Abatement Plan (AAP). To avoid inadvertent disturbance of the ACM by other parties
prior to commencement of CLS decommissioning, Project Profile of Asbestos Abatement
work in CLS at Penny’s Bay were prepared for the application of Environmental
Permit (EP) direct in August 2001. An EP has been issued in October 2001. As such, the environmental impacts that
may arise during asbestos abatement work are not evaluated further in this
report.
6.3
During the
operation of the shipyard, various chemicals (i.e. paints, lube oil, etc.) were
used and different chemical wastes (i.e. metallic slag wastes, ash) were
generated by many processes (i.e. plating, smelting, burning, etc.). Such chemicals might have been spilled
or leaked onto concrete floor and then subsequently into the subsurface soil
and groundwater. Extent of
contamination caused by historical shipyard operation as well as the proposal
of remediation measures have been addressedare discussed in Section 4X
of this Report. Therefore, the
environmental issues pertaining to contaminated soil and groundwater are not
discussed in this section.
6.4
This section
focuses on the management of waste arising from this Project, but excluding the
remediation of contaminated soil and asbestos abatement work. This section also describes the type
and estimated quantities of materials that will remain on site after relocation
of the shipyard operation, the waste arising due to the decommissioning of CLS
as well as the waste generation from the off-site treatment area at TKW. Recommendations for handling and
disposal of the identified wastes will be provided to minimise the waste
management implications.
Environmental Legislation, Standards and Evaluation
Criteria
6.5
The following
legislation relates to the handling, treatment and disposal of wastes in the
HKSAR and will be used in assessing potential impacts:
· Waste Disposal Ordinance (Cap 354);
·
Waste
Disposal (Chemical Waste) (General) Regulation (Cap 354);
· Land (Miscellaneous Provisions) Ordinance (Cap 28);
·
Public
Health and Municipal Services Ordinance (Cap 132) – Public Cleansing and
Prevention of Nuisances Regulations
6.6
The following
documents, circulars and guidelines which relate to waste management and
disposal in HKSAR will also be referred to during the study:
· Waste Disposal Plan for Hong Kong (December 1989), Planning, Environment and Lands Branch, Hong Kong Government Secretariat;
· Environmental Guidelines for Planning in Hong Kong (1990), Hong Kong Planning Standards and Guidelines, Planning Department;
· New Disposal Arrangements For Construction Waste (1992), Environmental Protection Department And Civil Engineering Department;
·
Code
Of Practice On The Packaging, Labelling And Storage Of Chemical Wastes (1992), Environmental Protection
Department;
· Waste Reduction Framework Plan, 1998-2007 (1998), Planning, Environment and Lands Branch, Hong Kong Government Secretariat;
· Works Branch Technical Circular (WBTC) No. 2/93, Public Dumps;
· WBTC No. 2/93B, Public Filling Facilities;
· WBTC No. 16/96, Wet Soil in Public Dumps;
· WBTC No. 4/98 & 4/98A, Use of Public Fill in Reclamation and Earth Filling Projects;
· WBTC No. 5/98, On Site Sorting Of Construction Waste On Demolition Sites;
· WBTC No. 5/99 & 5/99A, Trip-ticket System for Disposal of Construction and Demolition Material;
· WBTC No. 19/99, Metallic Site Hoardings and Signboards;
· WBTC No. 25/99, 25/99A & 25/99B, Incorporation of Information on Construction and Demolition Material Management in Public Works Subcommittee Papers;
· WBTC No. 12/2000, Fill Management;
· WBTC No. 29/2000, Waste Management Plan;
· Code of Practice on Asbestos Control (4 sets);
·
Code
of Practice – Safety and Health at Work with Asbestos; and
·
Code
of Practice on the Handling, Transportation and Disposal of Asbestos Waste.;
·
A Guide to the Chemical Waste
Control Scheme and A Guide to the Registration of
Chemical Waste Producer.
Chemical Waste
6.7
Under the Waste Disposal (Chemical Waste) (General)
Regulation all producers of chemical waste must register with EPD and treat
their wastes, either utilising on-site plant licensed by EPD, or arranging for
a licensed collector to transport the wastes to a licensed facility. The regulation also prescribes
the storage facilities to be provided on site, including labelling and warning
signs, and requires the preparation of written procedures and training to deal
with emergencies such as spillages, leakages or accidents arising from the
storage of chemical wastes. The regulation also requires the
waste producer to pack, label and store chemical waste properly before
collection.
Construction and Demolition (C&D) Materials
6.8
The current
policy relating to the dumping of construction and demolition (C&D)
material is documented in the Works
Branch Technical Circular No.2/93, “Public Dumps”. Construction and demolition materials
that are wholly inert, namely public fill shall not be disposed of to
landfills, but taken to public filling areas (PFAs) which usually form part of
reclamation schemes. The Land (Miscellaneous Provision) Ordinance requires
that dumping licenses be obtained by individuals or companies who deliver
public fill to PFAs. The licenses
are issued by the Civil Engineering Department (CED) under delegated powers
from the Director of Lands.
6.9
In addition
to the Works Branch Technical Circular, EPD and CED have produced a leaflet
entitled ‘New Disposal Arrangements for
Construction Waste’ (1992) which states that C&D material with less
than 30% by weight (or 20% by volume) of inert material (i.e. public fill) will
be accepted at landfill. If the
material contains more than 30% inert material by weight, the waste must be
sorted and sent to PFA and the non-inert material (i.e. C&D waste) can be
sent to landfill for final disposal.
6.10
The criteria
for evaluating the potential waste management implications are set out in Annex
7 of the EIAO-TM. The method for
assessing potential waste management impacts arising from the project follows
those presented in Annex 15 of EIAO-TM and include the following:
· Estimation of the types and quantities of the waste generated;
· Estimation of the timing of generation of each type of waste;
· Assessment of potential impacts from the management of solid waste with respect to potential hazards, air and odour emissions, noise, wastewater discharges and transport; and
· Impacts on the capacity of waste collection, transfer and disposal facilities.
6.11
Prior to SI
for land contamination assessment, site reconnaissance was undertaken during
December 2000 when the shipyard was still operational. A number of surface samples were
collected from certain areas of the site suspected as being impacted. Samples were collected at the following
locations (refer to Figure 6.1a for the site layout):
· Composite grab sample (Sample 1) of foundry wastes on ground adjacent to Building N.
· Composite grab sample (Sample 2) of foundry sands from foundry floor of Building L.
· Composite grab sample (Sample 3) of dark grey-black ash residue material from aluminium smelter in rear of Building D.
· Grab sample (Sample 4) of bright yellow powder from floor of electroplating shop of Building D.
· Grab surface soil sample (Sample 5) from dark brown surface crust on ground surface in the vicinity of an old solvent still.
6.12
The above
samples were all analysed for heavy metals, and chromium VI. VOCs were tested for some samples and
the results are summarised below.
According to the laboratory results, elevated levels of metals and PAHs
were noted.
Table 6. 1 Reconnaissance Soil Sampling Results (Metals)
|
Sample
1 |
Sample
2 |
Sample
3 |
Sample
4 |
Sample
5 |
Silver |
0.9 |
0.5 |
34.2 |
0.3 |
0.2 |
Arsenic |
2 |
7 |
18 |
11 |
2 |
Barium |
41 |
53 |
740 |
141 |
230 |
Cadmium |
0.4 |
4.2 |
5.2 |
0.5 |
0.4 |
Chromium |
100 |
2,344 |
421 |
9,223 |
30 |
Chromium VI |
N/A |
N/A |
N/A |
4,909 |
N/A |
Cobalt |
20 |
36 |
7 |
11 |
8 |
Copper |
102 |
929 |
209g/kg |
432 |
164 |
Molybdenum |
23 |
360 |
70 |
38 |
3 |
Nickel |
63 |
1,857 |
486 |
389 |
15 |
Lead |
29 |
626 |
1,031 |
118 |
90 |
Antimony |
1 |
15 |
30 |
6 |
2 |
Zinc |
66 |
1,491 |
674 |
308 |
382 |
Mercury |
1.3 |
<0.1 |
0.2 |
<0.1 |
<0.1 |
Note: Unit in mg/kg or otherwise specified.
Table 6. 2 Reconnaissance Soil Sampling Results (PAHs)
|
Sample 2 |
Sample 3 |
Sample 5 |
Naphthalene |
<700 |
1,330 |
<700 |
Acenaphthalene |
<433 |
913 |
<433 |
Acenaphthene |
<167 |
1,270 |
<167 |
Fluorene |
<180 |
4,610 |
<180 |
Phenanthrene |
<500 |
30,900 |
<500 |
Anthracene |
<320 |
2,320 |
<320 |
2-Methylnaphthalene |
<223 |
6,130 |
<223 |
Benzo(b,k)fluoranthene |
<1,067 |
471 |
<1,067 |
Benzo(a)pyrene |
<533 |
92 |
<533 |
Chrysene |
<467 |
1,080 |
<467 |
Fluoranthene |
<567 |
3,050 |
<567 |
Pyrene |
<867 |
12,300 |
<867 |
Benz(a)anthracene |
<433 |
496 |
<433 |
Indeno(1,2,3-cd)pyrene |
<200 |
<200 |
<200 |
Dibenz(a,h)anthracene |
<77 |
<77 |
<77 |
Benzo(g,h,i)perylene |
<223 |
<223 |
<223 |
Low MW PAHs |
<2,523 |
47,500 |
<2,763 |
High MW PAHs |
<4,434 |
17,500 |
<4,434 |
Total PAHs |
<6,957 |
65,000 |
<7,197 |
Note: Unit in mg/kg or otherwise specified.
6.13
As discussed
in Section 4, the decommissioning work is scheduled to start in July 2002 and
will be completed in December 2005.
Major activities to be carried out in relation to waste management to
this particular Project include:
· Site clearance;
· Building demolition;
·
Slope improvement works behind CLS;
· Land formation of CLS after decommissioning;
· Construction & operation of decontamination systems on- site and off-site; and
· TKW Decommissioning including site reinstatement, removal of chemical wastes and abandoned equipment.
6.14
The nature of
each type of waste expected to be generated over the course of this Project is
discussed below together with an evaluation of the potential environmental
impacts.
Demolition and Decommissioning Phase
6.15
Decommissioning
of CLS will consist of asbestos removal, decommissioning and demolition of the
twenty-five existing buildings/ workshops, and on-site treatment. As mentioned previously, asbestos
removal and details of treatment of contaminated soil (site remediation
technologies) will not be addressed in this section.
6.16
During
decommissioning and demolition, the following wastes are expected:
· Site clearance waste;
· C&D material;
· General refuse; and
· Chemical waste.
Slope Improvement Phase
6.17
As part of
the scope of decommissioning of CLS, slope improvement work will be carried out
in hill slopes behind CLS. Such
works will comprise cut slope and fill slope. The proposed slope works will generally consist of the
following activities:
|
|
Earthworks |
Slope trimming to improve gradient for landscaping works |
Soil Nailing |
Formation of holes into slope by drilling, steel bar installation and grouting. |
Drainage Improvement |
Construction of concrete drainage channels and provisions of subsoil drains |
Landscaping Works |
Grassing and tree planting. |
|
|
6.18
Waste arising
from slope stabilisation will include:
· Soil and rock from excavation;
· Concrete blocks;
· Vegetation; and
· General refuse.
Land Formation Phase
6.19
The subject
shipyard is relative flat and low lying with levels of formation varying
between +3.5 mPD and +5.5 mPD. The
land formation works will involve the filling of CLS to an average level of
+11.0 mPD requiring fill material of around 1.5Mm3. Works will also include:
· Provision of stormwater drainage system;
· Laying of utilities; and
· Landscaping works.
6.20
C&D
material will be generated from the above activities.
Remediation Phase
6.21
As discussed
in Section 4, there will be both on-site and off-site soil treatment at CLS and
TKW respectively. Pure
metal-contaminated soils in CLS will be solidified on-site whereas the other
contaminated soil will be excavated, packaged where necessary and transported
by trucks to the designated decontamination work site at TKW. Given this
arrangement, the types of waste generated at each stage in relation to
remediation are identified as follows.
Cheoy Lee Shipyard Site
6.22
Remediation
activities carried out at CLS will be primarily soil excavation and
solidification of metal-contaminated soil. During the excavation and soil solidification, the following
wastes would be generated.
· Contaminated soils;
· C&D material arising from the construction of the on-site solidification plant;
· Small quantities of chemical wastes including buried drums that hold chemicals and buried asbestos materials, and wastes in connection with the maintenance of backhoes & equipment for excavation; and
· Workforce waste.
Collection and Transportation of Waste from CLS to TKW
6.23
It is
proposed in Section 4 that contaminated soils from CLS will be treated at TKW
whilst other chemical waste will be collected by licensed collectors for
disposal at the appropriate licensed disposal facilities. Dump trucks will be employed to relay
the excavated materials from the point of excavation to the unloading point at
TKW.
6.24
Dioxin-contaminated
soils (as classified as chemical waste) that require extra care of handling
will be transported by roll-off trucks.
This provides the most effective way to control the handling of such
hazardous wastes and minimise the chance of spillage/ leakage during transportation.
Off-Site Treatment Works
6.25
While
constructing and operating the treatment work, wastes of the following
categories will be generated at TKW.
· C&D material arising from site preparation, setting up & commissioning of the decontamination plants,
· End products/ treatment residues of the decontamination processes,
· Chemical waste arising from the equipment/ plant maintenance, and
· Workforce waste from the plant operatives.
TKW Decommissioning Phase
6.26
After
successful completion of remediation at TKW, the subject site will be
reinstated/ restored to an environmentally acceptable condition. TKW Decommissioning will consist the
following:
· Decommissioning of the thermal desorption plant, the associate equipment and other decontamination system;
· Demolition of storage structures, associated drainage and leachate collection and treatment systems;
6.27
Wastes
anticipated from the above works will mainly be C&D material and scrap
metal. No significant waste
arising is expected for the decommissioning of the thermal desorption plant as
the whole plant will be dismantled and shipped back to the supplier.
Prediction and Evaluation of Environmental
Impacts
Demolition and Decommissioning Phase
Site Clearance Waste
6.28
It is
expected that the site clearance will involve limited clearance of vegetation
with low ecological value as the rare species shall be transplanted as
recommended in the Theme Park EIA and
also Section 8 of this report. No
insurmountable impact is expected if such waste is disposed of properly at
approved strategic landfills.
C&D Material
6.29
The
overriding concerns for building demolition will be safety and minimisation of
environmental impacts. To this
end, a top-down and non-blasting approach demolition method is selected and it
forms the basis of environmental assessment of this Project. C&D material will comprise unwanted
material generated during demolition. Based on the size of each building as
shown in the following table, it is estimated that around 10,000m3
C&D material will be generated.
6.30
Contaminated
residues remaining on the indoor building surfaces, floors and equipment would
cause environmental and health concerns if not handled properly during demolition. Site inspection revealed that three
buildings (namely Buildings D, J & L as shown in Figure 6.1a) with half of their indoor
surfaces are contaminated due to historical operation. Such material requires proper treatment
or removal prior to building demolition
Table 6. 3 Existing Buildings in CLS
Building ID |
Usage |
Size |
A |
Company Store |
9m x 46m |
B |
Plating, anodising and lab |
19m x 67m |
C |
Warehouse |
9m x 46m |
D |
Hull moulding and pressing workshop, aluminium smelter |
43m x 46m |
E & F |
Security guards quarters and staff canteen |
6m x 32m |
G |
Worker’s canteen |
9m x 14m |
H |
Dangerous Goods Stores |
3m x 18m + 9m x 10m |
I |
Machine Shop |
18m x 32m |
J |
Lost wax store |
18m x 32m |
K |
Fiberglass hull construction workshop |
43m x 46m |
L |
Foundry |
18m x 46m |
M |
Former rolling mill |
Removed prior to 1991 |
N |
Metal stamping |
9m x 14m |
O |
Sawmill and moulding shed |
24mx 73m |
P |
Leather dressing, stores, and vehicle maintenance shed |
15m x 37m |
R |
Fibreglass boat finishing |
47m x 47m |
S |
Boat finishing |
43m x 70m |
T |
Boat finishing and painting |
33m x 70m |
U |
Fire suppression pump house |
5m x 10m |
V |
Moulding lofting room, paint booth and mould mock-up building |
44m x 70m |
W |
Welding/ metal workshop |
25m x 25m |
X |
Shot-blasting |
11m x 26m |
Y |
Metal workshop/ hull finishing |
19m x 58m |
Z |
Metal boat/ metal sheet fabrication |
19m x 43m |
General Refuse
6.31
There are
several areas within the subject shipyard which have stockpiled materials. Surveys of the shipyard were conducted
in September 2001 to visually identify the waste remaining on site (summarised
in Figures
6.1b to 6.1ae).
The types of general waste are classified below:
· General debris;
· Workforce waste;
· Wood/ timber and railing of slipways;
· Steel hangars;
· Old furniture and racks;
· Ship wreckage;
· Wooden/ steel piers;
· Disused machines; and
· Scrap metals.
6.32
The storage
of general refuse has the potential to give rise to environmental impacts. These include water quality, if waste
enters nearby water bodies, odour and visual impacts. The site may also attract pest and vermin if the waste
storage areas are not well maintained and cleaned regularly. In addition, disposal of waste at sites
other than approved waste transfer stations or disposal facilities can also
lead to environmental impacts.
6.33
Provided that
the refuse is stored and transported in accordance with good practices and
disposed of at approved strategic landfills, the potential impacts will be
insignificant. It is expected that
the quantity will not exceed 1,000 tonnes steel and 5,000m3 general
debris.
Chemical Waste
6.34
During site
surveys in September 2001 (the survey findings are summarised in Figures 6.1b to 6.1ae), the following chemical wastes were
identified:
· Asbestos (findings already highlighted in AIR)
·
Leftover chemical residues
or deposits (i.e. metal slag, PAHs);
·
Acid containing battery cells;
·
Metal fines;
· Paint containers with uncured solvent-based paint; and
·
Waste oil and solvent drums.
6.35
Based on
visual observations, the quantities are estimated below:
Table 6. 4 Findings of Waste Survey
Chemical Waste |
Quantities (No. or otherwise
stated) |
Paint Cans |
46 |
Oil Drums |
10 |
Battery Cell |
35 |
Chemical Cans |
46 |
Chemical Powder Bags |
11 |
Suspected PCB containing Transformer |
1 |
BCF Sprinkler System in DG Stores |
6 |
Leftover Chemical Deposit |
100m3 |
Buried Chemical Drums |
3 |
Disused
Equipment such as transformer |
5 |
6.36
Chemical
waste may pose serious environmental, health and safety hazards if it is not
properly managed. These hazards
may include:
· Fire hazards;
· Adverse environmental effects from spills; and
· Toxic effects to workers.
6.37
To ensure
proper handling of such waste, the Demolition Contractor shall register with
EPD as chemical waste producer. As
shown above, the quantity is relatively small and will be readily accepted at
the Chemical Waste Treatment Centre (CWTC) at Tsing Yi or SENT Landfill. In addition, the storage, handling,
transport and disposal of chemical waste shall be in accordance with the Code of Practice on the Packaging, Labelling
and Storage of Chemical Wastes issued by EPD.
6.38
Wherever
possible, opportunities shall be explored to reuse and recycle materials. The Contractor responsible for
decommissioning the shipyard shall ensure proper sorting and segregation of chemical
wastes so that the wastes can be appropriately handled and treated. For
instance, oily waste containing high percentage of recyclable content can be
recovered at a licensed waste oil re-refinery plant. To maximise the opportunity for recycling/ reuse, during the
decommissioning stage, recoverable chemical wastes (in particular oil, paint
and solvent) shall be separated from the rest and collected by licensed
collector for recovery at licensed plant where the waste oil will undergo a
series of processes such as pretreatment, phase separation, and
multi-distillation. After that,
the re-refined oil can be blended with various additives for reuse (i.e.
lubricant, motor oil, etc).
6.39
Provided that
the mitigation measures and recommendations are strictly implemented, the
potential environmental impacts arising from the storage, handling and disposal
will be minimal.
Slope Improvement Phase
6.40
The scope of
the slope improvement works relevant to this Project is shown on Figure 6.2.
It is anticipated that the works will take around 1 year to
complete. The activities of the
proposed slope works behind CLS are summarised as follows:
Table 6. 5 Scope of Slope Improvement Works for CLS
|
|
Activities |
Quantity |
Soil Excavation |
40,000m3 |
Rock Excavation |
2,100m3 |
Soil Nailing |
634 nos. |
Raking Drains |
179 nos. |
6.41
Soil and rock
generated will be reused within the subject shipyard to the extent possible
(i.e. landscape berm formation).
The general refuse and vegetation will be transported off-site for
ultimate landfill disposal.
Land Formation Phase
6.42
Land
formation works will include the removal of seawall blocks and demolition of
jetties. Note that the general
removal of the upper section of the existing wall is not required as such
structure is significantly below the required formation level. However, in some locations the removal
of the seawall may be required to allow for construction of piled bridge
foundations (associated infrastructure works for the development of Theme Park,
Penny’s Bay Section of the Chok Ko Wan Link Road). The estimated quantity of C&D material generated is
around 5,000m3.
Remediation Phase
Cheoy Lee Shipyard Site
6.43
According to
the findings of land contamination assessment presented in Section 4, some
soils contaminated with heavy metals, TPH, SVOCs and dioxins of around 87,000m3
will need to be excavated and treated either on-site at CLS or off-site at
TKW. The potential air and water
quality impacts arising from the excavation and mitigation measures have been
addressed in the respective Sections of this Report.
6.44
In the trenching
investigation conducted from June to November 2001, the burn pit area (Area 3)
was found to have a few drums holding chemicals (resembling fibreglass resins)
inside and some asbestos corrugated cement sheets buried. Their exact quantities will be
confirmed until they are exposed during excavation. They shall be regarded as chemical wastes and their handling
and disposal procedures shall be in compliance with the Waste Disposal (Chemical Wastes) (General) Regulation.
6.45
As
recommended in Section 4 of this Report, on-site solidification of
metal-contaminated soil will be carried out after excavation and site
preparation. The solidified soil
can then be used as public filling materials. The quantity of treated soil would be roughly about 10%
(bulking factor) more than that of the contaminated soil, which is about
52,800m3.
Collection and Transportation of Waste
6.46
Contaminated
soil of around 39,000m3 will need to be moved between CLS and
TKW. Contaminated soil shall be
carried by trucks via a temporary access road along the south side of the
Lantau Airport Railway (LAR). The
trucks could carry the contaminated soil in various arrangements depending on
the type of contaminants. Contaminated soil earmarked for biopiling and
solidification could be trucked in bulk, placed in the rear of dump trucks with
capacities typically between 6 to 10 cum with appropriate cover such as
impermeable (HDPE) sheeting securely fixed in position over the material in the
hold to protect against wind and rain. The material will be moved from the shipyard via the
temporary access road to Road P2 then via the proposed temporary access road
along the LAR from Yam O to To Kau Wan, refer Figure 6.3.
6.47
Assuming the road
shipment of a total of around 9,000m3 of material for biopile
treatment (over a period of around 6 months) the average daily shipment might
be 58m3/day, which equates to between 6 and 10 laden trips per
day. However, allowing for the
actual programmed rates of excavation over the 6 month period the laden truck
trip rate is estimated to vary up to between 27 and 53 laden trips per
day. This equates to up to 3 to 5
laden trips per hour over 10 hours.
Precautionary measures to minimise environmental impacts include:
· Truck loading shall be monitored to ensure that loss of material does not take place during transportation.
· Transportation would be subject to the Contractors rescue and contingency plans.
· Limitation of the number of laden truck trips to 6 vehicles/hour.
· Speed limitation to 50km/hour.
6.48
At To Kau Wan the dump truck could
then deliver the material to the storage area where it would be placed within
the biopile stockpile by earth moving equipment. Similar arrangements will be carried out at the CLS storage
area for on-site solidification works.
This is one of various feasible material handling methodologies for
general contaminated material which is shown in Figures 6.4a and 6.4b.
6.49
Other more
significant waste material such as the material contaminated with dioxins shall
be placed in roll-off trucks and effectively containerised. This provides for
the most effective way to control the handling of such waste material.
6.50
The material contaminated with dioxin
shall be placed in top loaded roll-off containers, which have hard covers that
can be securely shut and back door for tip disposal. Based on an average waste material density of 1.89 tonnes
per cubic metre, the nett weight of a typical container with 6 to 12m3 of
waste would be around 11 to 22 tonnes. This is comfortably within the normal
range of capacity of the roll off truck.
6.51
Assuming the
road shipment of a total of around 30,000 m3 of dioxin contaminated
soil over a period of around 6 months the average daily shipment might be up to
192m3 per day. This might equate to about 16 to 32 laden trips per
day. Allowing for actual
programmed rates of excavation over the 6 months, the laden trip rate is
estimated to vary up to between 19 to 38
per day. This equates to up
to 2 to 4 trips/hour over 10 hours.
6.52
When the
trucks approach the TKW Site, they will approach from west well clear of the
east side of the site thereby avoiding any disturbance to the area where the
group of egrets was sighted.
6.53
At To Kau Wan the containerised
dioxin-contaminated material would be unloaded in the normal manner within the
enclosed material storage building and redistributed by small front-end loaders
to the required area of the building.
The storage building would be fully enclosed during operations to
prevent losses of contaminated material. The material storage building would
have a controlled internal drainage system to collect any leachate from the
contaminated material. The above
outline is one of various feasible material handling methodologies for dioxin
contaminated material which is shown diagrammatically in Figure 6.5. The leachate
collected shall be treated on-site at the centralised wastewater treatment unit
(a mitigation measures proposed in Section 7 of this Report for the on-site
treatment of thermal desorption area runoff, decontamination water and
wastewater from wheel washing) and subsequently tested for dioxin prior to discharge
into the stormwater drainage system.
No detectable dioxin in the effluent shall be allowed.
Risks of Road Accidents during Transportation of Waste
6.54
The road
transportation of contaminated material between Penny’s Bay and the off site treatment
area at TKW is required. The total volume of contaminated material is as
follows:
· Material to be treated using Thermal Desorption and other treatments as necessary (Roll Off Trucks : Containerised): 30,000m3 dioxin-contaminated soil.
· Material to be treated using Biopiles and/or Solidification (Dump Trucks : Bulk): 9,000m3.
6.55
The number of
laden truck movements are estimated based on average payloads as follows:
Method |
Total Shipment (m3) |
Payload per Trip (m3) |
Total Laden Trips |
Roll Off Truck (Containerised) |
30,000 |
6 - 12 |
2,500 – 5,000 |
Dump Truck (Bulk) |
9,000 |
6 - 10 |
900 – 1,500 |
Total |
39,000 |
-- |
3,400 – 6,500 |
6.56
It should be
noted that the environmental implications of losses of contaminated material primarily
concern laden trips because of the presence of the contaminated material. An
equal number of additional unladen trips will also be made from TKW back to
Penny’s Bay.
6.57
The road shipments
will be made at the time of excavation of contaminated material from the
shipyard in order to avoid the need for temporary stockpiles at Penny’s Bay.
Therefore the above shipments would be made over the 6 months excavation
period. The frequency of laden trips would therefore be between up to 19 to 38
per day for containerised shipments. The average frequency of laden tip truck
bulk shipments would be up to around 27 to 53 per day. Overall then the total number of laden
shipments, including both containerised and bulk material, would be up to
around 46 to 91 per day.
6.58
The proposed
truck movements pass along the temporary access road at Penny’s Bay then along
Road P2 at Yam O, then along the temporary access road along south side of the
LAR to the restricted TMCA road at To Kau Wan passing beneath the LAR and onto
a road controlled by Lands Dept./ New Airport Section to the TKW Site. The traffic on these roads is almost
entirely construction traffic.
Only one short section (390m) of road P2 is open to use by the
franchised buses for construction workers and a short section of road at To Kau
Wan (112m) is used by TMCA.
6.59
An estimate
of the number of vehicle accidents associated with the movement of laden
vehicles carrying contaminated material to and from To Kau Wan can be drawn
from TD statistics. For this purpose the most appropriate class of vehicle for
which statistics are available is the heavy goods vehicle. The number of
licensed heavy goods vehicles in 2000 was 2,903 and the total number of all accidents
involving a heavy goods vehicle was 90. The average mileage of all vehicles in
2000 was 23,000km/vehicle. For heavy vehicles however the annual mileage is
estimated to be higher at around 35,000km/vehicle. On this basis the total
mileage of heavy goods vehicles in 2000 would be around (2,903 x 35,000 =) 102
million km. The frequency of all accidents for heavy goods vehicles is (90 /
102 million km) = 0.9 x 10-6 accidents per vehicle-km. Since 80% of
all vehicle accidents in 2000 were classified as slight, the number of
significant accidents would be estimated to be around (0.2 x 0.9 x 10-6)
= 0.18 x 10-6 accidents per vehicle-km.
6.60
For dioxin
contaminated material, around 30,000m3 will be carried in vehicles
of between 6m3 and 12m3 capacity over a distance of
3.6km. The total laden vehicle distance travelled over the 6 months duration of
excavation is therefore up to (30,000 / 6m3 x 3.6km) = 18,000
vehicle-km. The estimated number of significant vehicle accidents involving
laden vehicles carrying dioxin contaminated material to To Kau Wan over the 6
months duration of excavation would be (18,000 x 0.18 x 10-6) = 3.2
x 10-3 or 0.3% risk of one accident occurring.
6.61
In the same
way for contaminated material for biopile and subsequent solidification
treatment, a total of 9,000m3 will be carried in vehicles of between
6m3 and 10m3 capacity over a distance of 3.6km. The total
vehicle distance travelled over the 6 months duration of excavation is
therefore up to (9,000 / 6m3 x 3.6km) = 5,400 vehicle-km. The estimated
number of significant vehicle accidents involving laden vehicles carrying
contaminated material for biopile and subsequent solidification treatment at To
Kau Wan over the 6 months duration of excavation would be (5,400 x 0.18 x 10-6)
= 0.97 x 10-3 or 0.1% risk of one accident occurring.
6.62 In the unlikely event that a significant incident did occur during the transportation of contaminated material it is important to employ the necessary precautions to avoid loss of any material with significant contamination. These measures include the use of roll-off trucks (containerised) of material contaminated with dioxin. In addition the trucks shall be accompanied by escort vehicle travelling ahead of the roll-off trucks to reduce the risk of accidents.
6.63
The thermal desorption treatment of
dioxin-contaminated material is expected to generate a total of 600m3
of non-aqueous dioxin condensate equivalent to 960 litres per day. This material will need to be
transported from To Kau Wan to the Chemical Waste Treatment Centre (CWTC) at
South East Tsing Yi. Such
shipments will be made by trucks.
Various possible transport scenarios are possible including that the
CWTR collects the condensate at a convenient location accessible by public
road. One such possibility is that
the condensate will be collected at Yam O. In this case the condensate would be taken from TKW by truck
along the temporary access road south of the LAR to Yam O and be collected by
CWTC at a convenient location along Road P2 at Yam O, refer Figure 6.6. The dioxin condensate
will be held in 200 litre drums which will be loaded into a container during
transportation. Transportation of
10 to 15 drums of dioxin condensate would be required two to three times per
week. On this basis a total of
around 152 to 228 laden shipments of dioxin condensate would be required over
the 2 years duration of treatment.
6.64
A total of
around 600m3 of dioxin condensate (the rate of condensate generation
will be discussed later in this section) will be transported by road between To
Kau Wan and Yam O over a distance of 1.7km for collection by CWTC over a 2 year
period. Road shipments of 10 to 15 drums (200 litres per drum) of dioxin
condensate would be required 2 to 3 times per week. The total laden vehicle
distance involved would be up to (594 / 2m3 x 1.7km) = 505
vehicle-km. The estimated number of significant vehicle accidents involving
laden vehicles carrying dioxin condensate per year would therefore be (505 x
0.18 x 10-6 / 2years) = 0.05 x 10-3 or 0.005% risk of one
accident occurring.
Consequences of Road Accidents during Transportation of Waste
6.65 Road transport of waste shall be substantially limited to within the Penny’s Bay reclamation area and other temporary access roads away from public roads between the point of excavation and TKW. Strict transportation procedures shall be followed to minimise the chance of road incident including speed control and the use of roll-off trucks (containerisation) of dioxin contaminated soil. No significant environmental and traffic impacts are envisaged as site access between CLS and TKW will be entirely on site access road (other than a short section of Road P2 open to franchised buses for construction workers and a short section of restricted road at TKW under the control of TMCA). Furthermore, no sensitive receivers are located nearby in the vicinity of the site access road. Mitigation measures to minimise the likelihood of road incidents have been proposed at the end of this section. As such, in the unlikely event that a significant incident did occur the possible impact would be spillage of contaminated soil on ground without any significant environmental impacts as the contaminants in soil would not be dispersed easily. Notwithstanding this, the following spill handling measures are proposed to minimise the consequences of spillage:
· Notify FSD immediately in case of major accidents or spillage;
· Fence off the impact area to avoid disturbance of contaminants and then migration of contaminants;
· Excavate the impacted soil immediately for off-site treatment;
· Workers shall put on proper personal protective equipment for workers during excavation as recommended in Section 4 in case of spillage of dioxin-contaminated soil.
· Properly decontaminate the handling and transport equipment in contact with the impacted soil.
Off-Site Decontamination Works
6.66
There will be
three major decontamination processes at TKW, viz. biopiling, thermal
desorption and solidification that generate wastes.
6.67
Soil treatment of non-dioxin-contaminated
soil: In biopiling,
off-gas from the piles of TPH-contaminated soil will be extracted and the
volatile organics will be stripped off by activated carbons before discharge
into atmosphere. As TPH is found to contain mainly non-volatile portions and
the VOCs emissions are not expected to be significant. The activated carbon would be used in
the initial phase (the rate of stripping of volatile contaminants will decrease
with decontamination period) and as back-up unit should the emissions exceed
the discharge limits. As such, the quantity of carbon used will not be
substantial, the activated carbons will not be subject to on-site regeneration
but will be reused by contractors who will recharge the spent carbon. If this
is not possible, it will be disposed of as chemical waste. It is estimated that some 1-2m3
of spent activated carbons will be generated each month for the first three
months of operation and the total quantity generated during the whole biopiling
period should be less than 30m3.
6.68
After
completion of biopiles, solidification is required to reduce the leachability of metals should the resultant soils contain high metals levels exceeding the action
levels for soil remediation. The solidified the resultant soil willcan be considered clean and canthen be used as public
filling materials. Since no
additives will be added during the process, tThe quantity of treated
soil would be roughly about
10% (bulking factor) more than that of the contaminated soil, which is about 9,900m3. Whenever the solidified material is to
be reused as filling material, they shall be put below at least 1m of clean
soil which provides adequate cover to avoid human contact.
6.69
Soil treatment of dioxin-contaminated soil:
The process of thermal desorption
is described in Section 4. Key
wastes generated are by-products of the emission control system and condensates
resulted from the quenching process.
The emission control system will cope with minor gas effluents from the
quenching process and fugitive effluents inside the plant. Spent filters and air phase activated
carbons of about 1.5 tonnes in total for final emission polishing will be
treated and disposed of as chemical wastes. (Note that the thermal desorption plant will employ a
catalytic oxidiser for treating the off-gas, activated carbon is only used as
back up for final polishing).
Deposits that are regularly dislodged from the bag filter will be
recharged into the beginning stage of the thermal desorption. Spent water phase activated carbon is
estimated to be about 10 tons over the project period. These dioxin-containing wastes
will be disposed of at the Tsing Yi CWTC for destruction as recommended in
Section 4 of this Report.
6.70
The resultant
condensate after thermal desorption would be liquids comprising non-aqueous and
aqueous phases. Assuming 20% moisture content of dioxin-contaminated soil, one
m3 soil would turn out 0.2m3
(or 200L) condensate in which 10% (i.e. 0.02m3
or 20L) is of non-aqueous phase whereas the rest of 90% (i.e. 0.18m3
or 180L) is of aqueous phase.
According to the SI results (as presented in Section 4) around 30,000m3
of dioxin-contaminated soil will need to be treated, therefore the total volume
of condensate generated is around 5,400m3. The volume of non-aqueous condensate (i.e. oil residue) is about 600m3 (equivalent to
3,000 nos. of 200L-drums).
6.71
While the
non-aqueous condensate will be collected and disposed of at CWTC at Tsing Yi, the
aqueous condensate will be treated on site through activated carbons where the
trace amount of soluble organics will be removed. The
treated aqueous phase
of the condensate
will be used to quench and rehydrate the treated soils, which are dry and powdery after thermal treatment. No monitoring of the quality of the
treated condensate is required as confirmation test will be carried out for the
treated soil.
6.72
Following
thermal desorption, solidification will take place by addition of cement to
demobilise the remaining heavy metals (not removed by thermal desorption). About 30,000 m3 of soil from
Area 3 of CLS is contaminated with metals and would be fed to the
solidification plant after thermal desorption for the removal of dioxin. Before feeding to the solidification
train, the incepted soil will be firstly screened of boulders, rubble and
cobbles that would hinder the solidification efficiency. The screened items or rejects which are
inert will be crushed on site into proper sizes before treatment. This will increase the volume of the
final product by 10%, which is regarded as clean filling materials giving about
33,000m3.
6.73
In summary,
around 42,900m3 solidified soil from TKW and 52,800m3
solidified soil from CLS suitable for public filling will be generated after
successful remediation. Whenever the dioxin solidified material is to be reused
as filling material, they shall be put below at least 3m of clean soil which
provides adequate cover to avoid human contact.
TKW Decommissioning Phase
C&D Material
6.74
Based on the
size of each storage structure, site drainage and leachate collection and
treatment systems, it is estimated that around 5,000m3 C&D
material and 500 tonnes steel will be generated. The C&D material will be disposed at PFAs and the metal
will be recycled, as such waste impact will be insignificant.
Summary of Waste Impact
6.75
The timing
and quantity of generation of each type of waste is summarised below:
Waste Type |
Prediction of Impact |
Building Demolition Phase
(July 2002 – September 2002) |
|
Site Clearance Waste |
As the subject shipyard is located on reclaimed land and the site is not heavily vegetated except along the northern and north-eastern boundaries of CLS, therefore during the demolition phase only limited amount (i.e. approximately 5% of C&D Material) of site clearance waste will be generated. |
C&D Material |
The demolition of existing buildings at CLS will generate approximately 10,000m3 C&D material. |
Workforce Waste |
The maximum daily number of workers on site will be around 100. Based on a waste generation rate of 0.65kg per person, it is estimated that the amount of general refuse will be in the order of 65kg/day. |
Steel |
Based on visual inspection of CLS, steel waste will be generated due to the demolition of steel hangars and steel piers. It is estimated that the quantity will not exceed 1,000 tonnes. |
General Debris |
General refuse were noted leftover the CLS after its relocation. It is estimated that the quantity will not exceed 5,000m3. |
Chemical Waste |
Various chemical wastes were noted during the site inspection. It is estimated that the quantity will not exceed 1,000m3 (assumed to be 20% of general debris). |
Slope Improvement Phase
(July 2002 – December 2003) |
|
Soil |
It is estimated that around 40,000m3 of uncontaminated soil will be generated during excavation.
|
Rock |
It is estimated that around 2,100m3 of uncontaminated rock will be generated during excavation.
|
Land Formation Phase
(October 2002 – July 2003) |
|
C&D Material |
The demolition of seawall and jetties will generate around 5,000m3 C&D Material. |
Remediation Phase
(November 2002 – February 2006) |
|
Contaminated Soil |
It is estimated that approximately 87,000m3 contaminated soil (30,000m3 dioxin-contaminated soil is regarded as chemical waste) will need to be excavated, of which 48,000m3 (metal-contaminated) will be solidified on-site and the remaining transported for off-site treatment at TKW. After both on- and off-site treatment, around 100,000m3 clean soil suitable for public filling will be generated. |
Chemical Waste |
The off-site decontamination works will comprise mainly 3 processes, biopiling, solidification and thermal desorption. It is estimated that less than 20 tons solid chemical waste will be generated, mainly spent filters (air phase and water phase) and around 600m3 liquid chemical waste will be generated throughout the remediation period. |
TKW Decommissioning Phase
(February 2006 – July 2006) |
|
C&D Material |
The demolition of storage buildings at TKW will generate about 5,000m3 C&D material and 500 tonnes steel. |
Construction and Demolition Phase
Good Site Practice and Waste Reduction Measures
6.76
It is not expected
adverse waste impacts would arise provided that good site practice is strictly
followed. Recommendations for good
site practice during the decommissioning and demolition activities include:
· Use waste haulier authorised or licensed to collect specific category of waste;
· Obtain the necessary registration and licences under the Waste Disposal Ordinance and the Waste Disposal (Chemical Waste) (General) Regulation from the Environmental Protection Department;
· Nomination of an approved person, such as a site manager, to be responsible for good site practice, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site;
· training of site personnel in proper waste management and chemical waste handling procedures;
· provision of sufficient waste disposal points and regular collection for disposal;
· appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers;
· separation of chemical wastes for special handling and appropriate treatment at a licensed facility;
· regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors;
· a recording system for the amount of wastes generated, recycled and disposed of (including the disposal sites);
· In order to monitor the disposal of C&D material and solid wastes at public filling facilities and landfills, and control fly-tipping, a trip-ticket system shall be included as one of the contractual requirements and implemented by the Environmental Team. One may make reference to WBTC No. 5/99 for details; and
· A Waste Management Plan (WMP) shall be prepared and this WMP shall be submitted to the Engineer for approval. One may make reference to WBTC No. 29/2000 for details.
6.77
Good
management and control can prevent the generation of significant amount of
waste. Waste reduction is best
achieved at the planning and design stage, as well as by ensuring the
implementation of good site practice.
Recommendations to achieve waste reduction include:
· segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal;
· to encourage collection of aluminium cans, paper waste and plastic bottles by individual collectors, separate labelled bins shall be provided to segregate this wastes from other general refuse generated by the work force;
· any unused chemicals or those with remaining functional capacity shall be recycled;
· use of reusable non-timber formwork to reduce the amount of C&D material;
· prior to disposal of C&D waste, it is recommended that wood, steel and other metals shall be separated for re-use and / or recycling to minimise the quantity of waste to be disposed of to landfill;
· proper storage and site practices to minimise the potential for damage or contamination of construction materials; and
· plan and stock construction materials carefully to minimise the amount of waste disposal and avoid unnecessary generation of waste.
6.78
In addition
to the above good site practice and waste reduction measures, specific
mitigation measures are recommended below for the identified waste arising to
minimise environmental impacts during handling, transportation and disposal of
these wastes.
Waste Recycling
6.79
To minimise
the amount of waste disposal to landfills, the general refuse (not
contaminated) shall be reused and recycled as much as practical. Waste sorting and segregation shall be
carried out in accordance with the following categories for recycling:
· Plastic (i.e. plastic bag, plastic bottle, plastic packaging, etc.)
· Rubber;
· Paper;
· Wood/ timber;
· Glass;
· Textile; and
· Metal (i.e. aluminium can, steel metal, ferrous metal, and non-ferrous metal).
Asbestos
6.80
Although not
covered in this Report, the removal shall follow the approved AAP and
conditions stipulated in the EP for Asbestos Abatement work in CLS at Penny’s
Bay and the Code of
Practice on the Handling, Transportation and Disposal of Asbestos Waste.
Chemical Waste
6.81
Removal Sequence: As asbestos removal will precede building
demolition, so the concern will be non-asbestos chemical waste. To avoid
disturbance of potential chemical waste during building demolition, all movable
objects including sand/ grit/ deposits inside the building under demolition
shall be cleared in advance.
“Movable objects” shall mean all items inside the building other than
those belong parts of the building structure or are anchored firmly on the
building structure/ existing ground. All movable objects including sand/ grit/
deposits shall be treated as chemical wastes and placed in drums and delivered
to a centralised covered area on site.
No mixing or off-site disposal of the waste shall be allowed. The non-removable objects shall be
covered with the heavy-duty polythene sheets for later disposal. Transportation and storage of the waste
shall be in accordance with the relevant chemical waste regulations. Particularly the requirement of spill
prevention measures, worker protection (e.g. PPE) and proper segregation from
other wastes shall be observed. Whereas all other chemical wastes
outdoors (except dioxin-contaminated soil which shall be transported by
roll-off trucks for added safety) shall be handled and stored in accordance
with Waste Disposal Ordinance and Waste Disposal (Chemical Waste) (General)
Regulation.
6.82
Workers
involved in the handling of chemical waste shall be suitably trained and shall
wear appropriate protective masks and clothing when handling such
materials. Chemical wastes shall
be handled according to the Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes. Spent chemicals shall be stored and
collected by an approved operator licensed collectors for disposal at licensed
facilities in accordance with the Chemical Waste (General) Waste Disposal (Chemical Waste) (General) Regulation.
6.83
Containers used
for the storage of chemical waste shall:
· Be suitable for the substance they are holding, resistant to corrosion, maintained in good condition, and securely closed;
· Have a capacity of less than 450 litres unless the specifications have been approved by the EPD; and
· Display a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations.
6.84
The storage
area for chemical waste shall:
· Be clearly labelled and used solely for the storage of chemical waste;
· Be enclosed on at least 3 sides;
·
Have an impermeable floor and bunding,
of capacity to accommodate 1100% of the volume of the largest container or
20% by volume of the chemical waste stored in that area, whichever is the
greatest;
· Have adequate ventilation;
· Be covered to prevent rainfall entering (water collected within the bund must be tested and disposal as chemical waste if necessary); and
· Be arranged so that incompatible materials are adequately separated.
6.85
Disposal of
chemical waste shall:
· Be via a licensed waste collector; and
· Be at a facility licensed to receive chemical waste, such as CWTC which offers a chemical waste collection service and can supply the necessary storage containers; or
·
Be a reuser of the waste, under
approval Be a
recycler of the waste, with waste disposal licence from the EPD.
Sorting of C&D Material On-site
6.86
The
Contractor shall separate the C&D material including steel, timber and
scrap metals from other wastes, as far as practical, and shall arrange for
recycling and reuse on site to the extent possible. All C&D materials arising from demolition work shall be
sorted on-site and be separated into different groups for disposal at
landfills, PFAs, or recycling as appropriate in accordance with WBTC No. 5/98. To maximise landfill life, Government policy
discourages the disposal of C&D wastes with more than 20% inert material by
volume (or 30% inert material by weight) at landfill. Inert C&D material (public fill) is directed to
reclamation areas or to an approved public filling area (PFA), where it has the
added benefit of offsetting the need for removal of materials from borrow areas
for reclamation purposes. Due to limited space at landfills, disposal at
reclamation sites or PFAs would be the preferred option. A trip-ticket system for disposal of
C&D material as detailed in WBTC No.
5/99 shall be followed.
Finally, a method statement for the sorting, processing and disposal of
C&D materials arising from demolition work shall be submitted by the
Contractor to the Engineer for his approval.
Building Indoor Surfaces Containing Contaminated Residues
6.87
Building sampling
shall be carried out prior to demolition to characterise the contaminants
present on the building surfaces, determine whether such residues are
classified as chemical waste, and identify suitable reagents for decontamination. After contaminants characterisation, a
Decommissioning Plan shall be prepared by the specialist Contractor
recommending the indoor remediation protocols as well as the demolition method
(preferably a top-down and non-explosive approach) for the Engineer’s approval. Those building containing contaminated
residues shall be decontaminated first before demolition. In general, the building
decontamination may include the following processes:
· Power washing;
· Scabbling;
· Grit blasting; and
· Confirmation testing.
6.88
Power washing
and grit blasting will produce secondary wastes, so scabbling is the preferred
method of cleaning. To ensure
effective and proper cleaning, adequate on-site supervision by competent
personnel is required.
6.89
After
completion of building decontamination, the material can be discarded as normal
C&D material. The chemical
deposits or residues from scabbling will be disposed of to CWTC for ultimate
disposal.
General Refuse
6.90
General
refuse shall be stored in enclosed bins or compaction units separated from
C&D material and chemical wastes.
No open stockpile of general refuse is allowed on site to minimise
environmental impacts. A reputable
waste collector shall be employed by the contractor to remove general refuse
from the site, separately from C&D material and chemical wastes, on a daily
or every second day basis to minimise odour, pest and litter impacts.
6.91
Aluminium
cans, paper waste and plastic bottles are often recovered from the waste stream
by individual collectors if they are segregated or easily accessible, so
separate labelled bins for their deposit shall be provided if feasible. Site
office waste can be reduced through recycling of paper if volumes are large
enough to warrant collection. Participation in a local collection scheme shall be
considered if one is available.
Slope Improvement Phase
6.92
The excavated
soil and rock shall be reused/ recycled within CLS as much as practical (i.e.
landscape berm formation). In
addition, a Waste Management Plan shall be prepared by the Contractor in order
to keep waste arising to a minimum and to ensure that waste is handled,
transported and disposed of in a suitable manner.
6.93
The design of
slope work shall be planned carefully to maximise the preservation of existing
profiles with stabilisation as necessary to minimise cutting and filling.
Land Formation Phase
6.94 The overall total of C&D material to be generated by this Project is estimated around 0.4Mm3. The C&D material will be reused and recycled as far as practicable in the land formation works within CLS site so as to minimise the amount of C&D material to be disposed of at PFAs.
Remediation Phase
Cheoy Lee Shipyard Site
6.95
On handling
contaminated soil, especially of dioxin-contaminated, site workers and the
backhoe operators shall be protected from skin contact and inhalation of soil
gas. The protection shall be
achieved by providing each worker/ operator sufficient personal protective
equipment, such as coverall, respirator, etc. and suitable training on handling
contaminated waste.
6.96
Chemical
wastes shall be handled in compliance with the provisions of Chemical Waste Disposal (Chemical Waste) (General) Regulations. The site contractors, workers and
operatives shall also be required to follow appropriate procedures on handling
chemical wastes according to the Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes.
6.97
Identified
asbestos waste shall be handled in accordance with the Project Profile of Asbestos
Abatement Work in CLS, however, the asbestos discovered in soil of Area 3 shall
follow the following requirements:
·
While the APCO requires registered
professionals to undertake the abatement work, the Waste Disposal Ordinance and the Waste Disposal (Chemical Waste) (General) Regulation provides control on the
packaging, labelling, storage, collection and disposal of asbestos waste. Asbestos wastes shall be handled in
accordance with the Code of Practice on
the Handling, Transportation and Disposal
of Asbestos Waste issued by the Environment and Food Bureau.
· Asbestos waste, by definition under the Waste Disposal (Chemical Waste) (General) Regulation, is categorised as chemical waste of which the arrangement of production, collection and disposal will follow the ‘trip-ticket’ system as with other chemical wastes. The registered asbestos contractor who is the waste producer shall appoint a licensed asbestos waste collector to collect the packaged asbestos waste and deliver to the designated landfill for disposal. Under the Waste Disposal Ordinance and Waste Disposal (Chemical Waste) (General) Regulation, directions of asbestos disposal shall be obtained from the EPD and prior arrangement with the landfill operator shall be made before disposal.
Collection and Transportation of Wastes
6.98
Dump trucks
will be extensively used for the transit of waste, other than material
contaminated with dioxin which will be transported by roll-off trucks between
the excavation area and TKW. The
following precautionary measures shall be taken to avoid spillage, wind erosion
and incident in transit.
· Transportation of contaminated soil shall be escorted to improve road safety;
· Strict speed limit shall be imposed on the whole length of the haul road;
· Never overload the trucks to prevent spillage of contaminated soils;
· Dioxin-contaminated material shall be transported in roll-off trucks (containers).
· Always cover the payload on each dump truck with strong and low permeable sheeting or the likes to withstand wind and rain while the truck is travelling; and
· Adequately but not excessively wet the payload to reduce dust generation.
6.99
As
dioxin-contaminated soil is classified as chemical waste, the trucks shall be
labelled, handled and transported in accordance with the Waste Disposal Ordinance and the
Waste Disposal (Chemical Waste) (General)
Regulation. In addition,
Chemical Waste Collection Licence under S.21 of the Waste Disposal Ordinance
shall be obtained for the collection and transportation of such chemical
waste. When the trucks approach
the TKW Site, they will approach from west well clear of the east side of the
site thereby avoid disturbance to the area where the group of egrets was
sighted.
6.100
Dioxin
condensate (oily residue) generated from the thermal desorption plant shall be transported in heavy duty
and sealable drums made of inert, chemical resistant and robust material, which
will then be collected by CWTC’s own fleets or licensed contractors which are
designed and licensed for the collection of hazardous and chemical wastes.
6.101
Finally, a contingency plan
shall be prepared by
the Contractor to spell out the necessary procedures to be taken and in case of
accident and/ or
emergency when transporting the contaminated soil to off-site location(s). All responsible parties and/ or persons
and their contact numbers shall be listed in the plan. When the barges approach the To Kau Wan Site, thev
should be kept away (minimim distance 100m) from the shore line on the east side
of the site to avoid disturbance to the egrety. They should also travel at
speeds lower than 10 knots within 500m of the egrety to minimize noise impacts.
Material Handling, Transportation and Storage
6.102 The movement of contaminated material between the shipyard and the off-site treatment area needs to be carried out in a controlled manner taking reasonable precautions to minimize potential losses that might otherwise have significant environmental impacts. The measures recommended need to take into account the degree of contamination of the material involved and the potential impact of losses. This subsection considers the requirements for material handling, transportation and storage in order to arrive at an appropriate scheme to minimise environmental risks in a cost-effective manner.
6.103 Material Handling and Transportation: Material contaminated with heavy metals, TPH and SVOCs will be handled in the established manner using bulk earth moving equipment for on-land works including excavation by excavators on site. Dump trucks with sealed rear gates will be used to move the contaminated material between the shipyard and the To Kau Wan works area. The contaminated material in the trucks shall be covered with impermeable sheeting (i.e. HDPE) to prevent ingress of rainwater during transportation.
6.104 Additional precautions relating to the material handling and land transportation for dioxin-contaminated soil are recommended. Roll-off trucks (containerised) are recommended to minimise the risk of material loss during material handling and transportation, particularly in the event of an incident. Direct loading of material into containers at the point of excavation is recommended to minimise double handling and any associated losses. The use of containers will also minimise the risk of material loss during transportation by road. Contingency plans will need to be prepared by the Contractor to specify the accident response action, containment and retrieval procedure.
6.105 Assuming 6 to 10m3 capacity trucks the total number of laden truck movements of excavated non-dioxin contaminated material from CLS to TKW would be between 900 to 1,500. On the basis that this excavation work was carried out over a period of 6 months this equates to around 6 to 10 truck loads per day.
6.106 The use of roll-off trucks (containerised) have been assumed for dioxin-contaminated material shipments. These containers would be reused after each shipment. The size of containers varies and a rated capacity between 6m3 and 12m3 has been assumed. Allowing for a shipment of between 6m3 and 12m3 (11.3 tonnes to 22.7 tonnes) of contaminated material and based on the estimated total volume of about 30,000m3 of dioxin-contaminated material, a total of between 2,500 and 5,000 truck loads would be required. One the basis that excavation work was carried out over a 6 month period this equates to around 16 to 32 truck roads per day.
6.107 Storage: A number of factors could affect the method of storage of material contaminated with dioxin. These include the need for and method and extent of transportation to the off-site treatment area, the available storage area and any potential need to move the material to an alternative treatment area.
6.108 The most economic method of storage is to stockpile the contaminated material in earth bunds covered by impermeable membranes to prevent wind erosion and exposure to rain. An impermeable base and drainage system is also required to collect the contaminated leachate. In this case the impermeable base could be formed using a reinforced concrete slab graded to drain leachate through filter membranes to channels and catchpits. The slab would provide a practical hard surface for material handling whilst preventing leakage of any contaminated material. The sides of the stockpiles could either be sloping at angles slightly less than the natural angle of repose of the contaminated material, or be formed using reinforced concrete walls to minimise storage space requirements.
6.109 Containerised storage of dioxin-contaminated material has been considered. This could involve the use of standard 20ft long containers. The contents of contaminated material may vary according to the type of container used. For the purpose of this estimate the volume of contaminated material has been assumed to be 11.7cum (24 tonnes including container self weight). The number of containers required for the total 30,000m3 quantity of dioxin contaminated material would therefore be 2,564. These could be stacked 3 containers high (2.59 x 3 = 7.8m) in a block formation occupying a total net area of 1.3ha. The stacking of these containers could be carried using a standard reach stacker or a fork lift truck. The stacking area could be formed using a gravel bed foundation or using a sealed pavement.
6.110 The containers would need to be scrapped after proper decontamination at the end of the project because of the health risks from dioxin contamination and the relatively high cost of verifying the effectiveness of any container cleansing works at the end of the project.
6.111 The stockpile method would involve forming a stockpile on a paved area. The side slopes of the stockpile would need to be around 30 degrees to horizontal to maintain adequate stability. Assuming a total height of the stockpile of 3 metres, a total net area of 1.5ha would be required.
6.112 A more land use efficient method of storage would use a stockpile contained within a reinforced concrete storage bin area. Assuming a height of 3 metres for the surrounding wall and a free stockpile height above the top of the wall of an additional 3 metres, the net area required for storage would be 0.66 ha. The storage bin solution preferred where site area is limited because of the more efficient use of available landuse.
6.113 The containerised storage option is not preferred because the containers would require either extensive cleaning and testing to verify they were completely decontaminated and suitable for general reuse or scrapping at the end of the project. The use of storage bins are also not preferred because of the larger volume of C&D material generated from the demolition of the retaining walls around the bin. Given that adequate space exists at To Kau Wan, the controlled stockpile storage method is preferred.
6.114 To further reduce impacts on air quality, the use of a structure over the storage area has been included. The proposed scheme involves a storage height of 5 metres with additional height for headroom and a roof. The roof structure would be in place prior to the deposition, storage or removal of material from the storage building.
6.115 The layout of the storage building is shown in Figure 4.15. Only one-sided operation is provided for within the storage building. The roofing will protect against rain and wind and as such, rainwater will not enter the storage area but will be diverted to the sides of the building and collected in gutters and drain pipes and discharged into the stormwater drainage system.
6.116 For the bulk storage of general contaminated material for solidification only, a stockpile is proposed for storage up to an overall height of 5 metres over a net storage area of 1.0ha. Material stored to the design height shall be covered using impermeable sheeting. To control surface runoff from the metal-contaminated soil stockpiled at CLS, the storage area shall be concrete paved or floor lined prior to stockpiling materials on top. Temporary drainage system shall also be constructed to control any potentially contaminated surface runoff from leaving the treatment/ storage area.
Treatment Area
6.117
As discussed
in Sections 3 and 4, the off-site treatment area will be temporarily used for
stockpiling of contaminated and treated soil, and soil remediation including
biopiling, solidification and thermal desorption. Chemical wastes/ by-products will be generated from such
operations and processes. During
soil handling and transportation, spillage or leakage may occur resulting the
potential contamination of the surfaces of housing unit. The bin structure for stockpiles,
containment structure and concrete floor at the treatment site shall be
decontaminated after completion of remediation. It is recommended that these structures be decontaminated by
scabbling and then be discarded as normal C&D material. The chemical deposits or residues from
scabbling will be disposed of at CWTC for ultimate disposal.
Off-Site Decontamination Works
6.118
Most of the
soils after treatment will turn to clean inert materials suitable for public
filling. The condensate as the end
product of the thermal desorption process and other chemical wastes (e.g. spent
activated carbons & filters) generated shall be temporarily stored in a
secure hut. Such waste will be
collected by licensed collectors and disposed of at the CWTC bi-daily to avoid
bulk storage at treatment site.
Pending collection, the chemical waste shall be packaged and where necessary
stored temporarily on-site in accordance with the Chemical
Waste Disposal
(Chemical Waste) (General) Regulation.
6.119
It was known that
the CWTC is able to handle the chemical wastes generated over the course of
this Project. However, prior arrangement shall be made to avoid compromising
the daily operation of CWTC.
Treatment of Oily Residue at CWTC
6.120 Though CWTC is designed to handle hazardous organic pollutants including PCB and dioxins, the following measures are proposed to ensure the handling of dioxin condensate arising from this Project will not compromise the performance & operation of CWTC:
· A batch of the oily condensate will be sent to CWTC for a performance test and treatment shall begin only after performance tests have been passed.
· Treatment of condensate shall be in batches with a campaign every week or every two weeks.
Precautionary Measures during Wet and Typhoon Seasons
6.121
The following
measures are recommended to minimise the water quality impact at the treatment
site during typhoon seasons:
· Surface runoff from the treatment site shall be directed into storm drains via adequately designed sand/ silt removal facilities such as sand traps, silt traps and sediment basins. Channels, earth bunds or sand bag barriers shall be provided on site to properly direct stormwater to such site removal facilities.
· Catch-pits and perimeter channels shall be constructed in advance of site preparation works.
· Open stockpiles on site shall be covered with tarpaulin during rainstorms. Measures shall be taken to prevent the washing away of soil into any drainage system.
· The storage area for metal-contaminated soil pending for on-site solidification at CLS shall be roofed and covered. In addition, run-on/ run-off control elements shall be constructed. Finally, the floor shall be concrete paved.
· A dedicated water treatment unit (standalone from the water treatment unit of the thermal desorption for polishing the aqueous condensate as shown on Figure 4.15) shall be constructed for the treatment of contaminated run-off from the thermal desorber, leachate collected from biopile and storage area and decontamination water from decontamination pad or wheel-wash basin. Direct discharge of such wastewaters shall not be allowed without proper treatment.
Equipment Decontamination Requirement
6.122
For
excavation and transport equipment at the CLS or treatment site, if it stays
within the contaminated zone, such as excavation and stockpiling areas, it
shall be decontaminated (typically steam cleaning) prior to leaving the
contaminated zone. The contaminated
zone shall need to be clearly defined with fencing. The exit of the contaminated zone shall have a
decontamination pad for cleaning of the equipment before it leaves the
zone. The decontamination water shall
be collected and disposed of at the on-site water treatment unit. Care shall be exercised by the
Contractor to prevent contamination of areas outside the contaminated
zone.
6.123
In treatment
area, particularly for a large-scale ongoing operation, separate equipment
shall be employed for transport of treated materials to prevent any potential for
recontamination. A “contaminated”
loader shall load only the contaminated soils into the decontamination system,
and a “clean” loader shall be assigned to remove the treated soils from the
stockpile at the outlets of the decontamination systems.
6.124
Lining of
trucks with plastic is recommended to prevent spills and leakage during
transport. Besides, draping of
plastic over the sides of trucks can minimise the amount of soil accumulates on
the outside of the body. For
transport within the contaminated zone, the cover fabrics/ plastic sheeting can
be reused depending on the truck and cover configuration, otherwise they shall
be dumped into landfill.
6.125
No water
discharge is allowed prior to on-site treatment.
Conclusion and Recommendations
6.126
The quantity
and quality of waste arising from this project have been assessed and
evaluated. With
the implementation of the recommended mitigation measures, minimal impacts are
anticipated. This EIA concludes that no unacceptable environmental
impact in relation to waste management will result from this Project. All potentially harmful contaminants/
wastes from CLS shall be handled, treated and disposed of in an appropriate
manner to avoid and minimise environmental impacts and risks to human
health.
6.127
Prior to decommissioning, the
Contractor shall
submit a Waste Management Plan (WMP) to the Engineer for his approval. Such a management plan shall be site specific, including
the collection of contaminated runoff, treated of contaminated runoff
from thermal desorption plant, designation of areas for segregation, temporary storage of reusable & recyclable material and chemical waste.
6.128
Prior to demolition of
buildings/ workshops, a Decommissioning Plan (detailing the indoor remediation
protocols as well as the demolition method) shall be submitted to the Engineer for his approval.
The plan shall detail the findings of
building sampling at those contaminated buildings, recommend indoor remediation protocols and identify suitable methods for surface decontamination.
6.129
Prior to transport of contaminated materials (general
contaminated soil, dioxin-contaminated soil and dioxin condensate) off-site for treatment, a Contingency Plan shall be prepared by the Contractor to the Engineer for his approval. The plan shall spell out the necessary
procedures to be taken, provisions for worker health and safety and in case of accident and/
or emergency when transporting the contaminated soil to off-site treatment
area. All responsible parties and/ or persons
and their contact numbers shall be listed in the plan.
6.130
Prior to the
operation of the treatment facilities at TKW, an Operational Plan setting out
the details of waste handling and treatment options, the planning and management
of the associated environmental and safety issues from waste reception to final
disposal shall be prepared by the Contractor to the Engineer for his
approval.
6.131
The following registration/
licence/ approval/ permit/ notification are required for the production, storage, collection, and
off-site treatment of chemical
waste:
·
Waste Producer Registration: The Contractor is
required to be registered under the Waste
Disposal (Chemical Waste) (General) Regulation;
· Waste Collection Licence: A Waste Collection Licence under the Waste Disposal Ordinance is required for the transport/ delivery of chemical wastes to off-site waste disposal facilities;
·
Waste Disposal Licence: A Waste Disposal Licence is required
for the operation of
the off-site treatment
facility a TKW for the treatment for dioxin-contaminated soil.
· Approval for Using Large Container: Approval is required under the Waste Disposal (Chemical Waste) (General) Regulation for using chemical waste container with a capacity exceeding 450L.
· Part A Notification: Prior notification to the Environmental Protection Department is required before any collection of Part A chemical waste.
· Noise Permit: A Noise Permit under Noise Control Ordinance is required for night-time operation of the decontamination system and transportation of contaminated soil by trucks to TKW at night.